First electricity from the new 139 MW wind farm of Polsat Plus Group and ZE PAK in Drzeżewo already on the grid

Polsat Plus Group and ZE PAK have produced and fed the first megawatt-hour of electricity into the grid from their wind farm in Drzeżewo, just 15 months and 6 days after breaking ground. The new wind farm will have a capacity of 139 MW, effectively doubling the companies’ installed wind power capacity. Full commercial operation is planned for the fourth quarter of this year.

Last updated 05/19/2025